PowerOptimal Elon® 100 Installation Checklist V1.03

NOTE: This Installation Checklist is intended for installers and not general users. Users should please refer to the User Manual, which can be found at www.poweroptimal.com/manuals. This is NOT a replacement for the Installation Manual. Installers must follow the installation instructions in the Installation Manual, which can be found at the above link. All Elon installations must be signed off by a registered electrician, who must issue a supplementary CoC.

Customer name

Date

Elon®

serial no.

Installation address

Installer name

Installer signature

  1. INSTALLATION INSPECTION CHECKLIST

No.

Action

Result

Units

DC Side Inspection (NOT a full solar PV installation checklist – we recommend PV GreenCard)

1

Check that all panels are mounted securely

🞏

2

Check that mounting structure is grounded

🞏

3

Check that all panels are the same power rating and model

🞏

4

Check all insulation on PV cables

🞏

5

Check that PV cable size is as specified for installation

🞏

6

Check that all connectors are securely fastened

🞏

7

Check that all PV cables are properly routed and secured

🞏

8

Check that DC circuit breaker OR DC isolator + fuse are installed within 2m of geyser & in line of sight

🞏

9

Check that no PV cables are coiled

🞏

10

Check that PV cables are connected to the solar input terminals on the Elon 100 and with correct polarity (see wiring diagram on last page)

🞏

AC Side Inspection

11

Check that AC isolator is installed within 2m of geyser & in line of sight

🞏

12

Check that AC wires are connected to the correct terminals on the Elon 100 (see wiring diagram on last page)

🞏

Elon 100 inspection

13

Check that Elon is installed within 2m of geyser (maximum wire length between Elon and geyser is 3m). If installed outside, the Elon should be protected from the elements and installed with glands facing downward.

🞏

14

Check that two wires run between the Elon’s “element” terminals and the “element” terminals on the green element adapter and that they are securely connected at both ends.

🞏

15

Check that two wires run between the Elon’s “thermostat” terminals and the thermostat, and that they are securely connected at both ends.

🞏

16

Check that all wiring is at least 2.5mm²

🞏

17

IMPORTANT: Check that element adapter’s male spade terminals are securely and correctly seated in the element’s female terminals. Do a tug test on each side to test that it is secure.

🞏

18

Check that ALL labels have been applied as per the label diagram in the Elon installation manual (installation diagram, “Warning! photovoltaic power source” and 2 x “Warning, Dual Supply”).

🞏

19

Check that controller (remote control) has been securely installed in an accessible place and that both ends of the communication cable are properly inserted.

🞏

  1. COMMISSIONING CHECKLIST (DC Clamp Meter required)

No.

Action

Result

Units

20

Confirm correct wiring and confirm DC polarity to Elon® as per basic wiring diagram after this table. Also confirm test meter wires are connected correctly, black to common!

🞏

21

Confirm correct voltages and currents of all connections through the following steps:

21a

Confirm open / closed thermostat voltages (11 – 14 V DC open, 0 V DC closed). Leave thermostat in closed position for rest of testing. If water is already at setpoint (e.g. 55 or 60 °C), indicated by a solid green light on the controller, increase thermostat temperature setting or open a hot water tap in the house to drain some hot water.

V DC (open)

V DC (closed)

21b

Confirm controller wire is connected properly. The connections should “click” into place and appropriate LEDs should indicate (be active).

🞏

21c

With dial on “SOLAR ONLY” and solar power flowing to element (green LED flashing), confirm same DC voltage to element as measured at solar terminals.

V DC solar

V DC element

21d

With DC clamp meter confirm that there is an active current through element by measuring the current of one of the wires going from Elon® to element.

A DC

21e

Turn dial to “MAINS ONLY”. Note that the Elon® will only switch to mains 5 min after mains power switch-on or reconnection. With mains power flowing to element (red LED flashing), confirm same AC voltage to element as measured at mains terminals (should be approx. 230V AC).

V AC mains

V AC element

21f

With AC clamp meter confirm active current through element of between 9 and 18 Amps depending on element rating.

A AC

22

If you used a test controller for commissioning, remember to plug the wire from the installed controller back into the Elon® and check functioning.

🞏

23

Set thermostat back to original setting.

🞏

24

Set control dial to setting “2” (the 6 o’clock position).

🞏

Basic wiring diagram for Elon® 100