PowerOptimal Elon® 100 Commissioning Checklist V1.02

NOTE: This Commissioning Checklist is intended for installers and not general users. Users should please refer to the User Manual, which can be found at www.poweroptimal.com/manuals. This is NOT a replacement for the Installation Manual. Installers must follow the installation instructions in the Installation Manual, which can be found at the above link. All Elon installations must be signed off by a registered electrician, who must issue a supplementary CoC.

Customer name

Date

Elon®

serial no.

Installation address

Installer name

Installer signature

Commissioning Steps / Tests

  1. Once installation is complete, do the following:
    1. Turn the control dial to "SOLAR ONLY".
    2. Switch on the AC & DC circuit breakers or isolators.
    3. Remove the covering from the solar modules.
    4. Switch on the geyser circuit breaker at the main DB.

No.

Action

Result

Units

2

Confirm correct wiring and confirm DC polarity to Elon® as per basic wiring diagram on next page. Also confirm test meter wires are connected correctly, black to common!

🞏

3

Confirm correct voltages and currents of all connections through the following steps:

3a

Confirm open / closed thermostat voltages (11 – 14 V DC open, 0 V DC closed). Leave thermostat in closed position for rest of testing. If water is already at setpoint (e.g. 55 or 60 °C), indicated by a solid green light on the controller, increase thermostat temperature setting or open a hot water tap in the house to drain some hot water.

V DC (open)

V DC (closed)

3b

Confirm controller wire is connected properly. The connections should “click” into place and appropriate LEDs should indicate (be active).

🞏

3c

With dial on “SOLAR ONLY” and solar power flowing to element (green LED flashing), confirm same DC voltage to element as measured at solar terminals.

V DC solar

V DC element

3d

With DC clamp meter confirm that there is an active current through element by measuring the current of one of the wires going from Elon® to element.

A DC

3e

Turn dial to “MAINS ONLY”. Note that the Elon® will only switch to mains 5 min after mains power switch-on or reconnection. With mains power flowing to element (red LED flashing), confirm same AC voltage to element as measured at mains terminals (should be approx. 230V AC).

V AC mains

V AC element

3f

With AC clamp meter confirm active current through element of between 9 and 18 Amps depending on element rating.

A AC

4

If you used a test controller for commissioning, remember to plug the wire from the installed controller back into the Elon® and check functioning.

🞏

5

Set thermostat back to original setting.

🞏

6

Set control dial to setting “2” (the 6 o’clock position).

🞏

Basic wiring diagram for Elon® 100

A diagram of a solar panel  Description automatically generated

Things to Remember